Inspector General Finds 4-Year Parts Audit Lapse

Posted: Updated:
TVA workers at the Watts Bar nuclear facility on Oct. 26, 2012, use the airlock as they leave the containment building area. (Credit: Michael Patrick/News Sentinel) TVA workers at the Watts Bar nuclear facility on Oct. 26, 2012, use the airlock as they leave the containment building area. (Credit: Michael Patrick/News Sentinel)

KNOXVILLE, Tenn. (AP) - A report by the Tennessee Valley Authority's inspector general said the federal utility missed quality assurance audits at the Watts Bar Nuclear Plant.

According to the Knoxville News Sentinel the Office of Inspector General said no audits were done on commercial-grade materials being used to build Unit 2 at the power plant in Spring City for four years. The report also noted TVA has taken steps to prevent a repeat of the lapse and has hired independent evaluators to review the materials in question.

The Nuclear Regulatory Commission cited TVA for the breakdown in auditing that allowed thousands of parts bought for the reactor project to bypass being documented as nuclear grade.

TVA said in a statement it has taken prompt and comprehensive action to correct the problem.

(Copyright 2013 by The Associated Press. All Rights Reserved.)

Powered by WorldNow
Powered by WorldNow
All content © Copyright 2000 - 2014 NewsChannel 5 (WTVF-TV) and WorldNow. All Rights Reserved.
For more information on this site, please read our Privacy Policy and Terms of Service.